Refurbishment of the Induction Coil
In the MOTOR Jirkov foundry, the following actions were performed:
- Determination of the coil damage extent.
- Conducting the pressure test.
- Documentation of the pressure test.
- Removal of the original coil filler around the entire circumference.
- Removal of the original fabric on the outer part of the coil around the entire circumference.
- Removal of the original epoxy on the outer part of the coil at the damaged area.
- Chemical cleaning of deposits outside the profile.
- Replacement of missing or damaged micanite spacers at the damaged areas.
- Bandaging the damaged coil leads and damaged threads with insulation tape.
- Twice impregnation of the inner part of the coil with varnish.
- Installation of new epoxy at the damaged areas.
- Installation of new fabric around the entire circumference.
- Conducting a conical removal.
- Optical inspection of the coil.
- Final inspection of the coil.
- Packaging and preparation for dispatch.
- Handling of the coil.
- Time for purchasing necessary items for installation.
- Cleaning and ensuring necessary actions.
Reference:
"Due to the insulation burn on the EGES furnace coil, we were looking for a quick and professional repair for our 4-ton coil. We received a high-quality refurbished coil back within a record 4 weeks and immediately put it into the furnace. We plan to send another coil for a complete overhaul to BVCOILS in August 2024."
- Ivan HotovĂ˝, Director of the MOTOR JIKOV Foundry Division.
Need to arrange for the refurbishment of an induction coil?
Please fill out the renovation form